Tuesday, March 15, 2011

Eberhard SMC is hoping to man up at Luther Burbank Middle School next week

You may remember that I posted that Eberhard SMC was awarded the architectural sheet metal contract on this project, along with Preferred Heating & A/C back in early January, but had not started work yet. Well I met with the Foreman (Raul Sanchez) running this project for Eberhard today who told me that they are only about 15% complete with their scope of work.

Thursday, March 3, 2011

Western Allied Picks Up Work On 2 Projects In My Area!

Western Allied Corporation has won the award for the tenant improvement work on the USC Health Sciences Building project that I reported on in January. Altmeyer & Son's has completed the core duct work and are no longer on the job.